top of page

UTE WATER PROJECTS

Anchor 1
-
16 Road Water Line Improvement ProjectThe District is installing approximately 2,600 feet of 8-inch water line on 16 Road from North of Cattle Drive to Q Road. The District’s Utility Maintenance department will begin construction the week of June 16, 2025. The project is estimated to be completed by mid-July. During this project, a section of 16 Road between P Road and Q Road will be closed to through traffic. Please refer to the map below for details. Access to residences will be maintained at all times. Construction hours will be during business hours, Monday through Friday.
-
20 1/2 Road and I Road Waterline Improvement ProjectThe District will install 2,000 feet of 2-inch waterline at 31 3/4 Road, north of B 1/2 Road, to improve the District's distribution system. Traffic control will be utilized for this project.
-
31 3/4 Road Waterline Improvement ProjectThe District will install 900 feet of 2-inch waterline extensions at 31 3/4 Road, north of B 1/2 Road. The purpose of the project is to improve the District's distribution system. Traffic control will be utilized for this project.
-
F ½ Parkway Project Phase 2The District will coordinate with the City of Grand Junction's efforts to construct a new traffic corridor along F 1/2 Road from 24 1/2 Road to 25 Road to install new water infrastructure. The District will install 3,550 feet of new 12-inch C900 PVC to replace the 12-inch AC pipe along 25 Road and new fire hydrants. Construction is anticipated to start in late July 2025.
-
Monument Valley Pump Station ProjectThe District will be installing a new pump station and pipelines to improve the District’s distribution system operations in the high-elevation areas of the Redlands.
-
Southside Transmission Main Waterline Replacement Project Schedule HThe District is planning to replace approximately 11,000 feet of 24-inch concrete pipe with 30-inch welded steel pipe from 36 ¾ Road and E Road to 38 Road and Horse Mountain Road.
-
West Morrison Court Waterline ReplacementUte Water Conservancy District is replacing approximately 1,600 feet of 8-inch water line on West Morrison Court. The District’s Utility Maintenance department will begin construction the week of March 24, 2025. The project is estimated to be completed in late April. During this project, materials will be delivered to the site and stored accordingly. The asphalt will be milled as part of the process. Work will begin in the cul-de-sac and progress towards Dakota Drive. Access to residences will be maintained at all times. Construction hours will be from 8:00 a.m. to 4:00 p.m. Ute Water crews will be performing maintenance on the north side of the Morrison and Dakota intersection on Thursday, May 1. During this time, access to Morrison Court will be available only from East Dakota between 9:00 a.m. and 6:00 p.m. Please refer to the map below for information regarding the detour. The detour is anticipated to last one (1) business day. There may be several planned water service outages during the project to ensure the safety of those working on the project and to connect water services to the new water line. The District takes great pride in leaving work sites clean following the completion of a project. The asphalt is tentatively scheduled to be replaced in May.
bottom of page