Please ensure Javascript is enabled for purposes of website accessibility
top of page

UTE WATER PROJECTS

Anchor 1
  • 10 Road Waterline Improvement Project
    The District will be replacing 6,250 feet of existing 8-inch water lines along 10 Road from Q Road to R Road. This project will include new fire hydrants as well as service connections. The project will include a new fire hydrant. Traffic control will be utilized in this project.
  • 23 Road Waterline Improvement Project
    Ute Water Conservancy District (District) is upgrading approximately 8,250 feet of 8-inch water line on 23 Road from K Road to L Road, then along L Road to Signal Rock Road. The District’s contractor for this project, Dirtworks Construction, LLC, will begin construction the week of September 16, 2024. The project is estimated to be completed in late November. During this project, a portion of 23 Road will be closed to through traffic between K Road and Signal Rock Road. The map below details the closure and detour route. Access to residences will be maintained at all times. Construction hours will be from 7:00 a.m. to 5:00 p.m.
  • 26 ½ Road Waterline Improvement Project
    The District is upgrading 650 feet of waterline from 6-inch to 8-inch PVC on 26 1/2 Road between Central Drive and G 3/8 Road. During this project, a portion of 26 1/2 Road between Central Drive and G 3/8 Road will be closed to thru traffic. See the documents below for more details.
  • F ½ Parkway Project Phase 2
    This project will be coordinated with the City of Grand Junction and will establish domestic water and fire line infrastructure for a new traffic corridor along F ½ Road, from 24 ½ Road to 25 Road. The District will be installing 2,100 feet of 8-inch and 3,550 feet of 12-inch PVC pipe and installing new fire hydrants.
  • Ox Bow Subdivision Waterline Replacement Project
    The District is planning to replace approximately 1,000 feet of 6-inch PVC pipe on Ox Bow Road between F 1/4 and F 1/2 Road. The District's contractor for this project, Stone Construction, LLC, will perform the line upgrade beginning the week of July 15, 2024. The project is estimated to be completed in mid to late August 2024. During this project, a portion of Ox Bow Road will be closed to through traffic between F 1/4 Road and F 1/2 Road. The map below details the closure and detour route.
  • Southside Transmission Main Replacement Project
    The District is planning to replace approximately 10,300 feet of 24-inch concrete pipe with 30-inch welded steel pipe from 36 ¾ Road and E Road to 38 Road and Horse Mountain Road.
  • Village 9 Waterline Replacement Project
    The District is upgrading approximately 3,300 feet of 8-inch and 6-inch waterline on Oxford Avenue, between Lynwood Street and 28 Road, and Hanover Circle and Gloucester Circle. The District’s contractor for this project, M.A. Concrete Construction, will perform the line upgrade beginning the week of September 16, 2024. The project is estimated to be completed in mid-to late December. During this project, a portion of Oxford Avenue, Hanover Circle, and Gloucester Circle will be closed to through traffic between Lynwood Street and 28 Road. The map below details the closure and detour route. Access to residences will be maintained at all times. Construction hours are from 7:00 a.m. to 5:00 p.m.
bottom of page