CurrentProjects

District Projects
The District will replace approximately 1,500 feet of 6-inch water line with an 8-inch water line in the Orchard Mesa area. Construction is anticipated to begin in the summer of 2026.
The District will install 900 feet of 2-inch waterline extensions at 31 3/4 Road, north of B 1/2 Road. The purpose of the project is to improve the District's distribution system. Traffic control will be utilized for this project.
The District continues to coordinate with the City of Grand Junction's efforts to construct a new traffic corridor along F 1/2 Road (Four Canyons) from 24 1/2 Road to 25 Road to install new water infrastructure.
The District will install 3,550 feet of new 12-inch C900 PVC to replace the 12-inch AC pipe along 25 Road and new fire hydrants.
PROJECT UPDATE (3/5/2026)
The subcontractor and crews are nearing completion on this project. On Monday, March 9th, there will be a planned outage as part of Southside Transmission Schedule H. Between 5:00 a.m. and 5:00 p.m., approximately 15 homes in the area of 38 Road and F 1/4 Road may experience low water pressure or a possible water outage while crews perform a tie-in on the Southside Transmission. Homes impacted by this outage received a reverse notification on March 4th and March 5th, and will receive another on March 9th. More information about this outage can be found in the Outage Center.
PROJECT UPDATE (11/19/2025)
Replacement work for this project will begin in the Sobre El Rio area within the next few weeks. Please refer to the attached map for details on how this work may affect the neighborhood. Access to all residences will remain open throughout the project. Construction will take place during regular business hours, Monday through Friday. Please refer to the map below for details on how this work may affect your neighborhood.

The District has contracted with Sunroc Construction to replace approximately 11,000 feet of 24-inch concrete pipe with 30-inch welded steel pipe, from 36 ¾ Road and E Road to Sobre El Rio Subdivision and Aldrea Vista Court.
There may be several planned water service outages during the project to ensure the safety of those working on the project and to connect water services to the new water line. Customers impacted by planned water outages will be notified at least 24 hours before the outage is scheduled to take place. Our primary form of communication directly with customers is reverse phone calls and/or text messages. Customers are encouraged to reach out to the District to verify that their contact information is updated.
The District will replace approximately 11,000 feet of 24-inch concrete pipe with 30-inch welded steel pipe, from Sobre El Rio Subdivision along Highway 6 to Rapid Creek Road. Construction is anticipated to begin in the fall of 2026.
The District will replace approximately 1,600 feet of 6-inch water line with an 8-inch water line in the Orchard Mesa area. Construction is anticipated to begin in the summer of 2026.